construction 30.10.2006 - 10.31.2006
on 30.10.2006, we launched the site at 8 clock with delivery of the mobile crane and the
first excavators work to develop the strip foundations. The first timber supply from the forest above Voglau reached the site and we began to debarking the
Strains with the pressure washer. On 31.10.2006 then the scarf stones were delivered and
placed on the strip foundations and in the evening filled with concrete.